Road surface repair works will be carried out at Kecskemét West interchange located at chainage 85, M5 Motorway between 23rd June and 8th July 2021 in both directions. During the repair works the on- and off ramps of Kecskemét West interchange are partially available pursuant to the works scheduled.

In the first phase the on- and off ramp of Kecskemét West interchange in the direction of Budapest will be closed from 23rd June to 30th June 2021 due to the repair works.

Due to the works, the on- and off ramp of Kecskemét West interchange in the direction of Szeged will be closed from 1st July to 8th July 2021.

Access to the motorway is possible on a diverted route indicated by yellow traffic diversion signs with using main roads No. 52, 54 and 445.

With introducing speed limit, there will be two lanes ensured for the travellers in both directions, however, during asphalting works with closing the slow lane, there will be only one lane available for the travellers. The directed traffic routs will be indicated by yellow traffic signs for the travellers.

During the pavement reconstruction works the maximum speed will be limited to 60 and 80 km/h.

Kecskemét West interchange Phase I. – onramp towards Budapest, off ramp towards main road No. 52 CLOSED

Diverted routs towards Budapest and Dunaföldvár

Kecskemét West interchange Phase II. – onramp from main road No 52 towards Szeged CLOSED

Diverted routs from main road No. 52 towards Szeged

 

Information about current traffic restrictions and diversions will be continuously provided by Útinform on www.utinform.hu website, AKA Zrt. on www.aka.hu website and the operator – AWAY Zrt. AKA Zrt. asks travellers to drive more carefully, with keeping the speed limit on the M5 motorway.
Unforeseeable events may result changes in the above mentioned schedule, AKA Zrt. reserves the right to modify the schedule of maintenance works.

We wish you a safe trip!